It really depends on how much concrete they're willing to pour in the cold.
There have been some internet rumors about "8 pours this week" but keep in mind that even though they are at ground level in one spot, they've still gotta get the other 75% of the block [[not even thinking about the tower yet) up to ground level.
The ground level pour that happened last Friday was a big deal, but keep in mind that the "first level basement" below it was poured on oct 8 - about two months ago. Furthermore, there are parts of the block where they haven't even poured the first level basement [[in fact, that's literally everywhere except where we have both a first and second level).
Basically, if we approximate square footage and the current velocity of construction, we will have the whole block foundation at ground level some time between march and may - just in time for steel in the summer as bedrock said.