Cass Tech - RFP# B10-0790-3
Sounds like they are serious about tearing the old Cass down this time. According to bid documents, DPS has already done a walk-through with contractors. Demolition was scheduled to begin at the end of August, but dates have been pushed back several times. Bids were due on Sept. 9th.

On a positive note, there are at least a dozen historic artifacts that have are to be preserved, including most plaques, the archways, stone details, etc.
Jared W. Finney High School - RFP B-10-0717-3
Complete teardown and rebuild. Bids are due October 13th.
Mumford High School [[2011) - RFP B-10-0716-3
Teardown and rebuild. Bids due September 14th.
Mackenzie PK-8 - RFP B-10-0718-3
Teardown and rebuild. Demolition to start October 5th.
Munger PK-8 - RFP B-10-0713-3
Teardown and rebuild. Demolition scheduled to start October 10th.
Wilbur Wright High School - RFP-11-0001-2-0-2010/nm
Wright was supposed to have been torn down five years ago, but nothing ever came of it. The bidding process to tear it down wrapped up in July, but there hasn't been any progress since.
Naturally, all the dates and locations are subject to change, as DPS and deadlines don't seem to work out. Does anyone with experience dealing with RFP's know how seriously they follow through on these?